Lutron Product Delivery Lead Time Update

Lutron’s lead times are improving. We are working hard to address the remaining issues and affected orders as quickly as possible. Please see an overview below of our current lead times by major product families. For representatives and customers with access, check myProjects, myOrders, and the Daily Digest email for the most up-to-date lead times and ship-date estimates. For questions, please reach out to your Lutron sales representative.

Current Lead Times - Updated 9/20/2023

    Current Lead Times
Caséta​   <2 Weeks​
Drivers    2-4 Weeks 
HomeWorks   2-4 Weeks *Alisse is 8 weeks
In-Wall Sensors   <2 Weeks​
Ketra / Finiré Downlights   2-4 Weeks
Ketra Lamps / Lamp Solutions   2-4 Weeks 
Ketra Linear   4-8 Weeks*G2 Non-Graze is 12 weeks
Quantum / Athena​​   2-6 Weeks
RA3   2-4 Weeks​
Shades   3-4 Weeks *Some fabrics are >4 weeks
Vive   2-3 Weeks ​*Wireless Receptacle-10 weeks
Wallbox   <2 Weeks
myRoom / Code Smart Guestroom   2-5 Weeks

 

Lead times are improving. For representatives and customers with access, check myProjects, myOrders, and the Daily Digest email for the most up-to-date lead times and ship-date estimates. For questions, reach out to your Lutron customer service representative. Legal Disclaimer. Last update 9/20/2023

Lead Gen Hospitality

Need a Rep?

Find a sales rep to help create, design, and deliver a complete solution for your workplace.
Lead Gen Hospitality 2

Have a question?

Let us help you choose the right solution for your job.